费城宣布多条街道重铺路面时间表

费城街道管理局专员Kristin Del Rossi宣布,本周起将临时关闭部分街道并限制停车,以进行路面重铺工作,预计8月底完成。

费城以下街道将进行重铺路面作业:

  • B ST, from E Nedro Ave to E Champlost  Ave.
  • E CHAMPLOST AVE, from B St to Hammond Ave.
  • CLARIDGE ST, from E Pike St to E Lycoming St.
  • D ST, from E Allegheny Ave to E Westmoreland St.
  • HURLEY ST, from E Allegheny Ave to E Westmoreland St.
  • CLOUD ST, from Plum St to Meadow St.
  • DITMAN ST, from Kinsey St to Meadow St.
  • PLUM ST, from Ditman St to Mulberry St.
  • GILLINGHAM ST, from Mulberry St to Tackawanna St.
  • ORTHODOX ST, from Mulberry St to Ditman St.
  • PEAR ST, from Mulberry St to Tackawanna St.
  • 69TH AVE, from N Broad St to Verbena Ave.

工程分三阶段:铣刨、井盖水电箱调整、铺路。各阶段在未来几月内进行。铣刨旧沥青预计白班进行,每条走廊需5天。井盖水电箱调整也白班进行,每条走廊2-3天。最后铺路预计白班进行,每条走廊3-5天,视天气而定。施工均在上午7点到下午4点进行。

临时“禁停”标志将在施工前张贴。请居民在张贴时驶离现场,避免车辆被拖。若车辆被拖,请联系警区确定位置。建议驾驶员在附近预留更多时间。