费城街道专员克里斯汀·德尔·罗西(Kristin Del Rossi)宣布,为配合9月23日当周的第二高速公路区铣刨工作,将临时封闭部分街道并实施停车限制。
以下街道在9月23日至27日(日间作业)期间铣刨作业:
- Suffolk Avenue, from Island Avenue to Lindbergh Boulevard
- Titan Street, from South 30th Street to South 31st Street
- South 29th Street, from Tasker Street to Wharton Street
- Fitzwater Street, from Grays Ferry Ave to South Broad Street
- Bainbridge Street, from South Broad Street to South 13th Street
- South Juniper Street, from Bainbridge Street to Fitzwater Street
- Catherine Street, from South Broad Street to South 7th Street
工作将在白天7点至下午4点进行,道路保持开放并设临时交通标志。居民需准备停车限制,活动前将有临时“禁止停车”标志。请移开车辆以免被拖,车辆被拖可联系警署。建议施工区域驾驶预留额外时间。铣刨旧沥青预计白班五天完成,调整井盖和重置电线盒需两到三天,最后铺路工作需三到五天,视天气而定。